Subject: NAS2-99090 June monthly report
Date: July 5, 2000
The following items were completed or worked on during
June.
- Installed new oil cooler, 2 new radiators and 2
turbo air coolers in aircraft. Required support structure and baffles.
- Finished fabrication and installation of variable
opening cooling air duct.
- Prefinished wing, booms, rudder, horizontal stabilator
and tip extensions.
- Updated web site with info on CC Heliplane Transport
- Fabricated electric cooling fan support and duct.
- Finished as much of the rotor testing as possible
on the test stand. Most of the month's effort was spent modifying the
test stand and rotor drive in order to test the rotor.
Rotor test comments:
The original prerotator design is no longer adequate
for the larger dia rotor. Not only is the rpm lower - requires greater
torque, but the hp and additional torque requirement is greater because
of the nearly 1.5 times blade area increase. In order for the engine to
turn at the higher rpm and hp needed for prerotation, the drive ratio
needed to be increased. There was not room on the end of the vertical
rotor drive shaft for a larger pulley, so we installed a smaller pulley
on the prop drive shaft. The smaller pulley also allowed us to use the
original special belt length, as the belt manufacturer would not make
us the longer low stretch belt required for larger pulleys (upper management
found out the belt was going on an airplane). This was not an ideal situation,
but in the interest of saving time and to confirm the rotor system was
stable, we had hoped the belt and pulley diameters would be adequate for
short duration runs. The small pulley at the high loads produced so much
scuffing (inner radius of the pulley will try to turn the belt slower
than the outer pulley radius), that the belt would start smoking and wear
very fast after only a short run. We went through 8 belts. To obtain a
little better belt life, we had to go back to the larger drive pulley.
This reduced the engine rpm and hp needed to obtain the desired rotor
rpm and reduced the pulley center line distance to the point where the
belt misalignment was so far off that the belt would sometimes climb up
and over the pulley groove, destroying the belt, belt guard and aluminum
support. Under these conditions there was only enough hp to get the rotor
up to 420 rpm.
In addition to the prerotator belt problem, we had
a problem with the high lateral stiffness of the test stand. A little
lateral softness as is in the aircraft is desirable and greatly reduces
these loads. A relatively simple modification to the test stand to provide
some lateral softness (still different than in the aircraft) caused another
problem. Any out-of-balance caused by rotor flapping, or u-joint drive
whip (caused because the u-joint is not on the spindle tilt axis) and
amplified by the increased distance between the blade teetering axis and
the blade center of gravity at low coning/lift (distance needed due to
the larger rotor dia and lower centrifugal force) had to be carried by
the cyclic push rods. If a disturbance under power (in this case when
collective is increased) causes the U-joint angle to exceed approximately
1 degree, then the spindle whip starts to diverge and increases cyclic
loads until the control rods bend. This whip is not rpm dependent, but
rather on u-joint deflection and torque. When the aircraft is flying there
is no torque load on the u-joint. For the tests we would have preferred
to pull collective after the clutch was released, but because of the belt
misalignment problem with the belt being too short, this was not possible.
It is apparent the rotor drive will have to be redesigned
and it seems we will need to finish the rotor proof testing in the aircraft
while it is anchored to the test pad. We had hoped to take the rotor to
a minimum of 450 rpm on the test stand and satisfy ourselves that everything
was OK before a final confirmation test was done in the anchored aircraft.
As a result of the time required to design and fabricate
a new prerotator, it will take at best 3 weeks before we can start the
rotor testing again. Therefore next flight will not occur until after
Oshkosh. We have known for some time that a better prerotator design was
needed, but since it had nothing to do with flight safety and in the interest
of proving our concepts as soon as possible it has had a low priority.
We hope to complete the design and detail the drawings by July 12th.
The following items need to be completed before the
rotor can be tested. Essentially the aircraft will be ready to fly after
completion of the rotor tests, provided no modifications are necessary
as a result of the rotor tests.
- Finish rotor test.
- Remove engine from test stand and re-install in
the CarterCopter.
- Complete installation of all electrical systems
including the voice alarms.
Installation of the prop with a new spinner will take
place after the rotor testing.
|